Project start: Lots A to E – November 2012
Project completion: Lot A – February 2013, Lot B – August 2013, Lot C – February 2013, Lot D – July 2013, Lot E – February 2013
Renovation and refurbishment of administrative buildings and relocation of municipal departments: Lot A – building Avenue des Alpes 18, Lot B – building Avenue des Alpes 22, Lot C – building Grand-Rue 73, Lot D – building Rue du Marché 8, Lot E – building Rue de la Gare 30
Energy standard: SIA 380/1
Project start: February 2014
Project completion: June 2014
Creation of an adult daycare centre and terrace
Energy standard: SIA 380/1
Bellevue adult daycare centre – Yverdon
Project start: November 2013
Project completion: September 2015
Construction of an adult daycare centre
Energy standard: SIA 380/1
Based on the plans by architect Hofmann & Gailloud Sàrl
Project start: October 2014
Project completion: December 2015
Conversion and consolidation of Building F
Energy standard: Minergie Label
Project start: December 2014
Project completion: December 2015
Construction of a 56-place crèche/nursery
Energy standard: SIA 380/1
Project start: June 2012
Project completion: August 2013
Vertical extension and insulation
Energy standard: SIA 380/1
Project start: November 2008
Project completion: December 2009
Construction of a multi-purpose building, including space for younger children, older children and a nursery
Energy standard: Minergie Label
Project start (new building): January 2003
Project start (Crocs building): January 2004
Project completion: June 2005
Construction of a school building and consolidation of Crocs building
Energy standard: Minergie Label